| 1. Getting
Started |
|
|
|
|
Responsibility of: |
|
|
a. Building Permits |
|
General Contractor or
Owner |
|
b. Zoning Boards |
|
General Contractor or
Owner |
|
c. Home Owners Associations |
|
General Contractor or
Owner |
|
d. Financial Institutions |
|
General Contractor or
Owner |
|
e. Insurance Agents |
|
General Contractor or
Owner |
|
f. Individual Subcontractors |
|
General Contractor or
Owner |
|
| 2. Site Preparation and Excavation |
|
Responsibility
of: |
|
|
a. Call Excavation Contractor
to |
|
General Contractor or
Owner |
|
confirm work
schedule |
|
|
b. Cut or Grade the entrance
or |
|
Excavation Contractor |
|
driveway |
|
|
c. Install culvert pipes and |
|
Excavation Contractor |
|
spread crushed
stone |
|
|
d. Clear building site and |
|
Excavation Contractor |
|
material storage
area |
|
|
e. Dig basement excavation, |
|
Excavation Contractor |
|
haul or store dirt |
|
|
| 3. Water (City or Well) |
|
Responsibility
of: |
|
|
a1. Contact City to confirm
work |
|
General Contractor or
Owner |
|
schedule |
|
|
b1. Install water system to
building site |
|
City Department of Water |
|
a2. Contact well water
contractor |
|
General Contractor or
Owner |
|
to confirm work
schedule |
|
|
b2. Drill well water |
|
Well Water Contractor |
|
| 4. Septic System and Drain Field |
|
Responsibility
of: |
|
|
a. Call septic contractor to |
|
General Contractor or
Owner |
|
confirm work
schedule |
|
|
b. Install septic system and |
|
Septic Contractor |
|
|
drain field |
|
|
| 5. Temporary Utilities |
|
Responsibility
of: |
|
|
a. Call contractors and
utility |
|
General Contractor or
Owner |
|
companies to confirm work |
|
|
schedules |
|
|
b. Install temporary toilet
system |
|
Porta-John Supplier |
|
|
or Porta-John |
|
|
c. Install temporary
electricity |
|
Electric Utility Company |
|
d. Install temporary
telephone |
|
Telephone Company |
|
|
| 6. Call for Inspections if necessary |
|
|
| 7. Footings |
|
Responsibility
of: |
|
|
a. Call contractors and
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Locate and dig footings
and |
|
Concrete Company or |
|
pier pads |
|
Excavation Contractor |
|
c. Install access pipe for
utilities |
|
Plumbing Contractor |
|
|
d. Call for footing
inspections |
|
Concrete Company |
|
|
e. Pour concrete foundation |
|
Concrete Company |
|
|
footings and pier
pads |
|
|
| 8. Termite Protection |
|
Responsibility
of: |
|
|
a. Call contractor and
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Apply termite protection |
|
Exterminator |
|
|
chemicals and/or
guards |
|
|
| 9. Foundation |
|
Responsibility
of: |
|
|
a. Call concrete contractor
to |
|
General Contractor or
Owner |
|
confirm work
schedule |
|
|
b. Install forms for poured
concrete |
|
Concrete Company |
|
|
foundation |
|
|
c. Call for foundation
inspection |
|
Concrete Company |
|
|
d. Pour concrete foundation |
|
Concrete Company |
|
|
e. Install waterproofing,
parging |
|
Waterproofing Company |
|
or insulation |
|
|
| 10. Sub-Floor System; Deck and Porch Floors |
Responsibility
of: |
|
|
a. Call carpentry contractor
to |
|
General Contractor or
Owner |
|
confirm work
schedule |
|
|
b. Install subfloor, beams
and/or |
|
Carpentry Contractor |
|
posts as required |
|
|
c. Construct deck and porch
floors |
|
Carpentry Contractor |
|
| 11. Backfill and Rough Grade |
|
Responsibility
of: |
|
|
a. Call excavation contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Backfill around foundation |
|
Excavation Contractor |
|
c. Rough grade slope for lawn |
|
Excavation Contractor |
|
| 12. Delivery of Log Home Package |
|
Responsibility
of: |
|
|
a. Call Log Home Package
Provider |
|
General Contractor or
Owner |
|
to confirm delivery
schedule |
|
|
b. Confirm amount of final
payment |
|
General Contractor or
Owner |
|
for Log Home
Package |
|
|
c. Confirm delivery charges if
separate |
|
General Contractor or
Owner |
|
from log home package
price |
|
|
d. Arrange to have Certified
Checks |
|
General Contractor or
Owner |
|
available |
|
|
e. Prepare material storage
area |
|
General Contractor or
Owner |
|
f. Make arrangements for proper |
|
General Contractor or
Owner |
|
equipment and/or ample
manpower |
|
|
to unload log home
materials package |
|
|
g. In the case of a handcrafted
log home |
|
General Contractor or
Crane |
|
and the large size
logs being used, a |
|
Company |
|
|
crane must be on
site |
|
|
| 13. Unloading & Storage of Materials |
|
Responsibility
of: |
|
|
a. Unload Log Home Materials
and |
|
General Contractor or
Owner |
|
store as recommended
by your |
|
|
log home materials
provider |
|
|
b. Check all materials received
against |
|
General Contractor or
Owner |
|
the shipping manifest
or materials list |
|
|
| 14. Weathertight or Dry-In Construction |
|
Responsibility
of: |
|
|
a. Call log home materials
provider |
|
General Contractor or
Owner |
|
to confirm schedule |
|
|
b. Erect 1st floor log walls |
|
Builder or Owner |
|
|
c. Install 1st floor partition
walls and |
|
Carpenter or Owner |
|
|
second floor system |
|
|
d. Erect 2nd floor log
walls or construct |
|
Carpenter or Owner |
|
|
2nd floor exterior
framed walls |
|
|
with log siding |
|
|
e. Construct all roof systems
and sheathing |
Carpenter or Owner |
|
|
f. Install all exterior doors and
windows |
|
Carpenter or Owner |
|
|
g. Install all fixed glass |
|
Carpenter,Owner or Glass |
|
Company |
|
|
| 15. Roofing |
|
Responsibility
of: |
|
|
a. Call roofing contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install roofing felt or
titanium paper, |
|
Roofing Contractor |
|
|
flashing, shingles or
metal |
|
|
| 16. Fireplace & Chimney |
|
Responsibility
of: |
|
|
a. Call masonry contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Erect fireplace and
chimney |
|
Masonry Contractor |
|
|
| 17. Plumbing |
|
Responsibility
of: |
|
|
a. Call plumbing contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install rough plumbing
system |
|
Plumbing Contractor |
|
|
c. Call for plumbing inspection
if needed |
|
Plumbing Contractor |
|
|
| 18. Heating, Ventilation and Air Conditioning (HVAC) |
Responsibility
of: |
|
|
a. Call HVAC contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install rough HVAC ductwork
and equip |
|
HVAC Contractor |
|
|
c. Call for HVAC inspection if
needed |
|
HVAC Contractor |
|
|
| 19. Electrical |
|
Responsibility
of: |
|
|
a. Call electrical contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install rough electrical
wiring and |
|
Electrical Contractor |
|
|
service panel(s) |
|
|
c. Call for electrical
inspection if needed |
|
Electrical Contractor |
|
|
| 20. Framing Inspection |
|
Responsibility
of: |
|
|
a. Call for framing
inspection |
|
General Contractor or
Owner |
|
| 21. Interior and Exterior Concrete Work |
|
Responsibility
of: |
|
|
a. Call concrete contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Pour concrete floors,
driveways |
|
Concrete Company |
|
|
and walkways |
|
|
| 22. Ceiling Insulation |
|
Responsibility
of: |
|
|
a. Call insulation contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install ceiling insulation |
|
Insulation Contractor |
|
|
| 23. Wall Insulation and Soundproofing |
|
Responsibility
of: |
|
|
a. Call insulation contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install wall insulation
and |
|
Insulation Contractor |
|
|
soundproofing as
needed |
|
|
| 24. Interior Walls and Ceilings |
|
Responsibility
of: |
|
|
a. Call drywall contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install sheetrock, mud and
tape |
|
Drywall Contractor |
|
|
c. Call carpentry contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
d. Install wood tongue &
groove |
|
Carpentry Contractor |
|
where needed |
|
|
| 25. Paint, Stain and Wallcoverings |
|
Responsibility
of: |
|
|
a. Call painting contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Apply interior and
exterior |
|
Painting Contractor |
|
|
chinking and
caulking |
|
|
c. Apply exterior paint, stain
and |
|
Painting Contractor |
|
|
preservatives |
|
|
d. Apply interior paint, stain
and |
|
Painting Contractor |
|
|
wallcoverings |
|
|
| 26. Finish Floor Coverings |
|
Responsibility
of: |
|
|
a. Call flooring contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install hardwood flooring |
|
Flooring Contractor |
|
|
c. Install ceramic tile |
|
Flooring Contractor |
|
|
d. Install padding and carpet |
|
Flooring Contractor |
|
|
| 27. Interior Finish and Trim Work |
|
Responsibility
of: |
|
|
a. Call carpentry contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install interior doors and
hardware |
|
Carpentry Contractor |
|
c. Install interior window and
door trim |
|
Carpentry Contractor |
|
d. Install baseboard and shoe
mold |
|
Carpentry Contractor |
|
e. Install wall moldings, chair
rails, etc. |
|
Carpentry Contractor |
|
f. Install cabinets and
countertops |
|
Carpentry Contractor |
|
g. Install vanities, towel bars
and mirrors |
|
Carpentry Contractor |
|
h. Install closet shelves,
poles |
|
Carpentry Contractor |
|
and hardware |
|
|
i. Install stair treads,
railings |
|
Carpentry Contractor |
|
and balusters |
|
|
j. Install tub and shower
doors |
|
Carpentry Contractor |
|
k. Install drapery rods |
|
Carpentry Contractor |
|
| 28. Finish Plumbing |
|
Responsibility
of: |
|
|
a. Call plumbing contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install plumbing fixtures
and |
|
Plumbing Contractor |
|
|
appliances |
|
|
c. Call for final inspection |
|
Plumbing Contractor |
|
|
| 29. Finish HVAC |
|
Responsibility
of: |
|
|
a. Call HVAC contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install final HVAC equipment
and test |
|
HVAC Contractor |
|
|
c. Call for final inspection |
|
HVAC Contractor |
|
|
| 30. Finish Electrical |
|
Responsibility
of: |
|
|
a. Call electrical contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install fixtures, appliances
and |
|
Electrical Contractor |
|
|
outlet covers, etc. |
|
|
c. Call for final inspection |
|
Electrical Contractor |
|
|
| 31. Exterior Finish and Trim |
|
Responsibility
of: |
|
|
a. Call carpentry contractor to
confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Install window and door
trim |
|
Carpentry Contractor |
|
c. Install fascia and rake
boards |
|
Carpentry Contractor |
|
d. Install soffit and porch
ceilings |
|
Carpentry Contractor |
|
f. Install gable louvers and
soffit vents |
|
Carpentry Contractor |
|
g. Install garage door and door
opener |
|
Garage Door Specialists |
|
h. Install gutters and
downspouts |
|
Roofing Contractor |
|
|
| 32. Landscaping |
|
Responsibility
of: |
|
|
a. Call landscaping contractor
to confirm |
|
General Contractor or
Owner |
|
work schedule |
|
|
b. Finish grading, seeding,
sodding, |
|
Landscaping Contractor |
|
flowers and
shrubbery |
|
|
| 33. Final Building Inspection |
|
Responsibility
of: |
|
|
a. Inspect work of
subcontractors and |
|
General Contractor or
Owner |
|
make punch list |
|
|
b. Review punch list (concerns)
with |
|
General Contractor or
Owner |
|
contractors |
|
|
c. Re-inspect building after
corrections |
|
General Contractor or
Owner |
|
and accept work |
|
|
d. Obtain lien waivers and
approve final |
|
General Contractor or
Owner |
|
payment |
|
|
e. Call for final building
inspection |
|
General Contractor or
Owner |
|
f. Obtain occupancy permit |
|
General Contractor or
Owner |
|
g. Notify financial institution
of completion |
|
General Contractor or
Owner |
|
h. Notify insurance company of
completion |
|
General Contractor or
Owner |
|
i. Switch insurance to home owner's
policy |
Owner |
|
|
j. Notify any other agencies of
completion |
|
Owner |
|
|
| Welcome to Your
New Home!! |
|
|
|
|
|
|
|
|
|